Southbound I-55 work to begin
Published 12:00 am Wednesday, November 21, 2007
The DOTD will be working on the southbound I-55 between I-12 and La. 3234 (University Boulevard/Wardline Road) for concrete repairs.
The project is scheduled for Dec. 3, 2007 through Dec. 11, 2007, during which time the inside lane of I-55 southbound will be closed. Work will take place on Mondays and Tuesdays from 6 a.m. to 6 p.m.
The DOTD expects minimal delays resulting from this construction project but encourages drivers to use US 51 as an alternate route.
For more information, contact Nick Macaluso at 985-375-0190 or via e-mail nmacaluso@dotd.louisiana.gov.
Additionally, he can be reached by fax at 985-375-0249.
For any additional questions or comments about any DOTD projects, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail them at customerservice@dotd.la.gov. The center is open 7 a.m. – 6 p.m. Monday through Friday and 9 a.m. – 1 p.m. Saturday.